A project’s critical path is CEGHI. The expected finish time and the variance of each activity are as follows. Activity A B C D E F G H I Expected FT 2 5 3 6 4 5 3 1 5 Variance 10 4 15 14 10 15 20 5 6
a. the expected completion time of the project. F. 34 .
b. the variance of the project F. 99
To determine the expected completion time of the project and the variance of the project, we need to calculate the earliest finish time (EFT) for each activity and the total project duration.
The earliest finish time (EFT) for each activity is the sum of the activity's expected finish time (FT) and the EFT of the preceding activity on the critical path.
Activity A:
EFT(A) = FT(A) = 2
Activity B:
EFT(B) = FT(B) + EFT(A) = 5 + 2 = 7
Activity C:
EFT(C) = FT(C) + EFT(B) = 3 + 7 = 10
Activity D:
EFT(D) = FT(D) + EFT(C) = 6 + 10 = 16
Activity E:
EFT(E) = FT(E) + EFT(D) = 4 + 16 = 20
Activity F:
EFT(F) = FT(F) + EFT(E) = 5 + 20 = 25
Activity G:
EFT(G) = FT(G) + EFT(F) = 3 + 25 = 28
Activity H:
EFT(H) = FT(H) + EFT(G) = 1 + 28 = 29
Activity I:
EFT(I) = FT(I) + EFT(H) = 5 + 29 = 34
Therefore, the expected completion time of the project is 34 (EFT(I)).
To calculate the variance of the project, we need to sum the variances of the activities on the critical path.
Variance(A) = 10
Variance(B) = 4
Variance(C) = 15
Variance(D) = 14
Variance(E) = 10
Variance(F) = 15
Variance(G) = 20
Variance(H) = 5
Variance(I) = 6
Total Variance = Variance(A) + Variance(B) + Variance(C) + Variance(D) + Variance(E) + Variance(F) + Variance(G) + Variance(H) + Variance(I)
= 10 + 4 + 15 + 14 + 10 + 15 + 20 + 5 + 6
= 99
Therefore, the variance of the project is 99.
Answer to Question 1: F. 34
Answer to Question 2: F. 99
To learn more about total variance visit-
https://brainly.com/question/9431483
#SPJ11
You want to compare the batting average of all the players on the league's baseball teams. Which type of chart would be best for this purpose? a.Pie b.Bar c.Line d.Column
Answer: B.) Bar
Explanation: When trying to compare batting average of all players on the leagues baseball team, the batting average of the players in each team is measured and the data grouped by team. When measuring changes, differences or comparison, the bar chart and line chart seems to be the best for such purposes. However, depending on whether the changes in measured data is large or small, the bar chart seems best suited in cases where large differences exists, while line graphs are better when small differences exist between measure data.
Answer:
B.) Bar
Explanation:
how do you think your company's stakeholders would feel about your company simply adjusting to local management practices
Stakeholders' feelings about adjusting to local management practices would vary depending on the context and their individual interests.
How might stakeholders feel about a company's adjustment to local management practices?However, in general, stakeholders' feelings about a company adjusting to local management practices would depend on various factors such as the specific context, the nature of the adjustments, and the stakeholders' interests.
Some stakeholders may appreciate the company's adaptation as it demonstrates a commitment to local values, culture, and practices.
It may help build stronger relationships with local communities and enhance the company's reputation.
On the other hand, some stakeholders may have concerns about the potential impact on the company's global standards, consistency, and overall performance.
Balancing the interests of different stakeholders and considering the long-term implications would be essential in decision-making related to adjusting to local management practices.
Learn more about Stakeholders
brainly.com/question/30241824
#SPJ11
consider the market for supervillain masks. if there was one firm in the market the profit-maximizing quantity would be 400. if the market instead was perfectly competitive, the quantity would be 800. the market is actually a cournot duopoly with two identical firms that are in equilibrium. the quantity produced by each firm is going to be
The quantity produced by each firm is going to be less than 400.
The perfectly competitive market produces the maximum output
What is the market?
In the field of economics, a market is a collection of mechanisms that allow for the exchange of goods and services between parties. The majority of markets rely on sellers providing their goods or services to purchasers in exchange for money, however, parties may exchange goods and services by barter. The entire number of buyers and sellers in the area or region under consideration is referred to as the market. Earth, as well as several nations, regions, states, and cities, maybe the subject. The worth, expense, and cost of the goods traded depend on the forces of supply and demand in the market. Perfect competition, oligopoly, monopoly, and monopolistic competition are the four most common types of market arrangements. The relationships between sellers and other sellers, sellers, and customers, etc.
To learn more about market click on the given link:
https://brainly.com/question/25369230
#SPJ4
Which of the following is NOT a problem caused by monopolies?
Select one:
Low quality
Fewer new products
Poor customer service
More competition
Answer:
Poor customer service
Explanation:
Poor customer service
A problem that is not caused by monopolies is More competition.Thus the correct answer is D.
What is a monopoly?A monopoly refers to a situation when the market of particular goods and services is captured by a single entity or owner and restricts entry by controlling the activities.
They aim at limiting the amount produced for the market, which leads to charging more. This results in cutting back on economic welfare and consumer surplus.
As they are the single seller in the market which shows that there is no competition in the market, who challenges them. The problem of more competition is not caused by monopoly.
Therefore, Option D is appropriate.
Learn more about Monopoly, here:
brainly.com/question/13939056
#SPJ2
Question 1 of 10
An investment that you bought for
profit
and sold for
made a
500;600
500;400
600;400
600;500
Answer:
500;600
an investment
A business student is preparing for the Graduate Management Admission Test (GMAT) so he can get into a good graduate business school. He knows that any money he spends on a tutor will be worthwhile if he can improve his scores. He's heard that there is a great tutor in his local community but has no idea who she is. Marketing does not occur in this situation because
Answer:
For the parties to connect, there seems to be no way.
Explanation:
Marketing should be about fulfilling the expectations and wishes of consumers, generating demand, influencing different players, requiring interaction that can be carried out by the other groups and individuals.
For marketing, this same four components needed are:
Two or maybe more parties to expectations that are unmet. An appetite and capacity to be fulfilled on their part. A means enough for parties to connect. To share everything.And according to the format prescribed throughout the problem, the business student realized he wanted a tutor for his performance to be enhanced. He discovered that throughout his local neighborhood, a wonderful teacher is readily accessible but uncertain of her identification to express it. He can interact with her towards his tuitions across multiple channels as she contributes to something like the surrounding community.
Answer:
. .
Explanation:
Ethical behavior is a subset of which skillset?
professional skills
technical skills
professional conduct
interpersonal skills
Answer:
C). Professional Conduct
Explanation:
Ethical behavior is characterized as the obedience of moral principles like fairness, honesty, and equity. Such behavior recognizes the individual diversity and offers equal rights and respect to the dignity and integrity of every individual. It is one of the significant aspects of 'professional conduct' which promotes professionalism, healthy work relationships, mutual understanding, and maximize the output. Thus, option C is the correct answer.
Answer: Professional conduct is the answer
Explanation:
I just took the quiz and got the answer right
When you click on a word or an object within a Web site that directs you to another page or Web site, you
have followed a
hyperlink
road
leader
trail
Answer:
Hyperlink
Explanation:
In computing, a hyperlink, or simply a link, is a digital reference to data that the user can follow or be guided by clicking or tapping. A hyperlink points to a whole document or to a specific element within a document. Hypertext is text with hyperlinks. The text that is linked from is known as anchor text.
What should be included in all career objectives? interest in new challenges, relevant skills, technological expertise interest in a specific position, relevant skills, benefit to employer interest in a specific field, relevant skills, salary expectations interest in new knowledge, relevant skills, salary expectations
Answer:
B. interest in a specific position, relevant skills, benefit to employer.
Explanation:
Career objectives can be defined as an optional part of a curriculum vitae (resume) used by job applicants to give a brief description about their interest in a specific position, relevant skills, experience and potential benefits to an employer.
In order to increase your chances of being invited for a job interview, it is advisable that you include a clear career objective in your resume so as to make it compelling and convincing to hiring managers.
As a job applicant, what you should include in all career objectives is an interest in a specific position, relevant skills, and benefit to employer because it is one of the sections to be noticed first.
Generally, career objectives should be limited to a maximum of two or three lines of text or sentences and typed at the top of a resume, just below your contact information and name so as to quickly catch an employer's attention.
Calculate China’s RGDP growth rate in 2006, the growth rate of real GDP per person in 2006 (using the approximation formula), and the approximate number of years it will take for real GDP per person in China to double if the 2006 economic growth and population growth rates are maintained.
China’s RGDP growth rate in 2006 was _______ percent. Round up your answer to the first decimal. China’s growth rate of real GDP per person in 2006 (using the approximation formula) was ______ percent. Round up your answer to the first decimal.
It will take China approximately _______ years to double its real GDP per person. Round up your answer to a full number (no decimals).
Answer:
China’s RGDP growth rate in 2006 was 8.2% percent. Round up your answer to the first decimal. China’s growth rate of real GDP per person in 2006 (using the approximation formula) was 7.7% percent. Round up your answer to the first decimal.
It will take China approximately 9 years to double its real GDP per person. Round up your answer to a full number (no decimals).
Explanation:
Note: This question is not complete. The complete question is therefore provided before answering the question as follows:
In 2005 China's RGDP was 7,394 billion yuan. In 2006 its RGDP was about 8,000 billion yuan. China's population was 1,306.6 million in 2005 and 1,313.1 million in 2006.
Calculate China's RGDP growth rate in 2006, the growth rate of real GDP per person in 2006 (using the approximation formula), and the approximate number of years it will take for real GDP per person in China to double if the 2006 economic growth and population growth rates are maintained.
China's RGDP growth rate in 2006 was _______ percent. Round up your answer to the first decimal. China's growth rate of real GDP per person in 2006 (using the approximation formula) was ______ percent. Round up your answer to the first decimal.
It will take China approximately _______ years to double its real GDP per person. Round up your answer to a full number (no decimals).
The explanation to the answer is now given as follows:
a. Calculate China’s RGDP growth rate in 2006. Round up your answer to the first decimal.
This can be calculated using the following formula:
China’s RGDP growth rate = (2006 RGDP - 2005 RGDP) / 2005 RGDP = (8,000 - 7,394) / 7,394 = 0.0820, or 8.2%
b. Calculate the growth rate of real GDP per person in 2006. Round up your answer to the first decimal.
This can be calculated using the following formula:
China’s RGDP per person growth rate = (2006 RGDP per person - 2005 RGDP per person) / 2005 RGDP per person ............... (1)
Where;
2006 RGDP per person = 2006 RGDP / 2006 population = 8,000 / 1,313.1 = 6.09245297387861 billion yuan
2005 RGDP per person = 2005 RGDP / 2005 population = 7,394 / 1,306.6 = 5.65896219194857 billion yuan
Substituting the values into equation (1) above, we have:
China’s RGDP per person growth rate = (6.09245297387861 - 5.65896219194857) / 5.65896219194857 = 0.077, or 7.7%
c. The approximate number of years it will take for real GDP per person in China to double if the 2006 economic growth and population growth rates are maintained. Round up your answer to a full number (no decimals).
To calculate this, the rule of 70 is used as follows:
Number of years for Real GDP per person to double = 70 / China’s RGDP per person growth rate = 70 / 7.7 = 9 years
Dried Fruit Corp. has had a valid S Corp election in effect at all times since its incorporation. The Dried Fruit Corp. stock is owned one-third by Raisin and two-thirds by Prune. All shareholders are US resident citizen individuals. At the beginning of the current year, Raisin's basis in his shares was $108,000 and Prune's basis in her shares was $36,000. During the current year, Dried Fruit Corp. earned $648,000 of net income from operations. Raisin's share was $216,000; Prune's share was $432,000. On December 31st, Dried Fruit Corp. distributed Grapeacre (real property) having a fair market value of $216,000, and a basis of $144,000, to Raisin and Plumacre (real property) having a fair market value of $432,000 and a basis of $396,000, to Prune. How much gain does Prune recognize as a result of this transaction? $36,000 $0 $72,000 $108,000
The gain does Prune recognize as a result of this transaction is $36,000. The correct answer is (a) $36,000.
Since Dried Fruit Corp. has had a valid S Corp election in effect at all times since its incorporation, the corporation's income is passed through to its shareholders, and they are responsible for paying taxes on their respective shares of the income. Raisin's share of the net income was $216,000, and his basis in his shares was $108,000, so he does not recognize any gain or loss when he receives Grapeacre with a fair market value of $216,000 and a basis of $144,000. Prune's share of the net income was $432,000, and her basis in her shares was $36,000, so she has a total basis of $72,000. When she receives Plumacre with a fair market value of $432,000 and a basis of $396,000, she recognizes a gain of $36,000 ($432,000 fair market value - $396,000 basis - $0 liabilities = $36,000 gain). Therefore, the answer is $36,000.For more such question on transaction
https://brainly.com/question/1016861
#SPJ11
The gain does Prune recognize as a result of this transaction is $36,000. The correct answer is (a) $36,000.
Since Dried Fruit Corp. has had a valid S Corp election in effect at all times since its incorporation, the corporation's income is passed through to its shareholders, and they are responsible for paying taxes on their respective shares of the income. Raisin's share of the net income was $216,000, and his basis in his shares was $108,000, so he does not recognize any gain or loss when he receives Grapeacre with a fair market value of $216,000 and a basis of $144,000. Prune's share of the net income was $432,000, and her basis in her shares was $36,000, so she has a total basis of $72,000. When she receives Plumacre with a fair market value of $432,000 and a basis of $396,000, she recognizes a gain of $36,000 ($432,000 fair market value - $396,000 basis - $0 liabilities = $36,000 gain). Therefore, the answer is $36,000.For more such question on transaction
https://brainly.com/question/1016861
#SPJ11
How important is money
Answer:
very important
Explanation:
money is a global income source for everyone. we all have different types but it is all still money. now say one country got rid of money and had people pay for stuff using other things. if china did that lots of different countries wouldn't be able to get stuff from there unless they had so much of that product they could just give it up.
a machine center can produce 175 units per day at 100% utilization. demand is 75 units per day and suppliers are capable of delivering raw materials to support production of 125 units per day. if demand doubles, the flow rate will be
A machine center can produce 175 units per day at 100% utilization. demand is 75 units per day and suppliers are capable of delivering raw materials to support production of 125 units per day. if demand doubles, the flow rate will be
Given
Capacity=175 unitS
Demand=75 units
Supply=125 units
Now
Demand doubles=75*2=150 units
Now,flow rate=Least of (demand, supply, capacity)
=Min(175,150,125)=125 units
Answer D)125 units
Materials or substances used in the first stages of producing or manufacturing items are known as raw materials.
On commodity markets across the world, raw materials are commodities that are purchased and sold. Because raw materials are production factors, businesses trade them on the factor market.
To know more about raw materials visit:
https://brainly.com/question/13160417
#SPJ4
The risk associated with the unlikelihood that one of the key members will be struck by lightning would most likely be handled by which of the following?
A) Mitigating
B) Retaining
C) Ignoring
D) Transferring
E) Avoiding
Answer:
B) Retaining
Explanation:
The risk retaining refers to the risk in which the company takes the decision that represents the responsibility for some specific risk i.e. opposed to the risk transfer over and above to the insurance company
Here the risk retain is adopted when the doing cost is less than the fully or partially cost
In the given situation, since it is mentioned that the risk is attached with the unlikelihood and struck from lighting so this is to be handled by retaining
hence, the correct option is B. Retaining
The most important actors in the company's microenvironment are ________.
A. publics
B. suppliers
C. competitors
D. customers
E. company departments
The most important actors in the company's microenvironment are A. publics, B. suppliers, C. competitors, D. customers, and E. company departments. Publics: Publics refer to any group or individual that has an interest in or is affected by the company's activities.
This can include the general public, government agencies, media, and advocacy groups. Publics are important because they can influence the company's reputation and success through their opinions, actions, and support. Suppliers: Suppliers are the companies or individuals that provide the resources and materials needed for the company's operations.
They play a crucial role in the company's supply chain and can directly impact the quality, availability, and cost of the products or services offered by the company. Competitors: Competitors are other companies or organizations that operate in the same industry and offer similar products or services. They are important because they create competition in the market, which can drive innovation, influence pricing strategies, and affect market share.
To know more about company visit:
https://brainly.com/question/30532251
#SPJ11
1) Inflation represents the rate of increase of the average price of goods. If inflation decreases from 10% to 5%, does the average price of goods decrease? Explain.
No, the average price of goods does not decrease when inflation decreases from 10% to 5%.
Inflation represents the rate of increase in the average price of goods and services over time. When inflation decreases, it means that the rate of price increase has slowed down, but it does not imply a decrease in the average price itself. Even with a lower inflation rate, prices can still continue to rise, albeit at a slower pace.
The percentage of inflation indicates the extent of price increase compared to the previous period. If the inflation rate decreases from 10% to 5%, it means that prices are still increasing but at a slower rate. For example, if an item was priced at $100 at the beginning of the year, with a 10% inflation rate, its price would increase to $110. However, with a 5% inflation rate, the price would increase to $105. While the rate of increase has decreased, the average price of goods has not decreased.
Therefore, it is important to differentiate between a decrease in the inflation rate (a decrease in the rate of price increase) and an actual decrease in the average price of goods, which would indicate deflation.
Learn more about Inflation
https://brainly.com/question/31108471
#SPJ11
Over the course of a customer’s lifetime of reading a weekly
magazine priced at $4 per issue, what is the value of the magazine?
Assume a customer acquisition cost of $12, a retention cost of $0,
pr
The total number of issues the customer is anticipated to buy, together with the accompanying expenditures, must be taken into account in order to determine the worth of a weekly magazine throughout the course of a customer's lifetime.
Assuming 52 issues per year, let's assume the consumer will be expected to subscribe to the magazine for a total of 5 years, or 260 issues. Given that there is no mention of a customer retention cost, we will treat the $12 client acquisition cost as being equal to $0. By deducting the whole costs from the total money made by the reader, the worth of the magazine may be determined. The revenue in this scenario is calculated by multiplying the price per issue ($4) by the total number of issues. (260). Total revenue: $4 x 260 = $1,040 Total costs = $12 for customer acquisition. Total revenue - total costs equal $1,040 - $12 = $1,028. This is the value of the magazine. As a result, the magazine is worth $1,028 to the purchaser over the course of their lifetime.
learn more about customer here:
https://brainly.com/question/31192428
#SPJ11
Quantify the steel structure design that comprises the following: 14 rows of steel 16K2 joists; 165 linear feet each (5.5 lbs/ft) 14 rows of W27 x 114; 145 linear feet each Gauge metal decking that will be used to support the future concrete floor (145' x 165') *Account for connections by adding an additional 10%, when applicable. *ROUND YOUR FINAL ANSWERS TO THE NEAREST DIGIT 16K2 joists : tons W27 x 114: tons Gauge metal decking: sf
16K2 joists: approximately 159 tons, W27 x 114: approximately 28 tons, Gauge metal decking: approximately 23,925 square feet.
To quantify the steel structure design, we calculate the total weight of the 16K2 joists and W27 x 114 beams by multiplying their respective linear feet with the weight per foot. Considering the additional 10% for connections, the approximate total weight for the 16K2 joists is 159 tons, and for the W27 x 114 beams, it is 28 tons. For the gauge metal decking, we multiply the length and width to get the total square footage, which is approximately 23,925 square feet. These calculations provide an estimation of the quantities required for the steel structure design.
Learn more about approximately here:
https://brainly.com/question/31646822
#SPJ11
According to Hofstede, in which country would it be most
difficult to implement transformational leadership?
According to Hofstede, the following countries such as Malaysia, China, ,Saudi Arabia, Japan would be the most difficult to implement transformational leadership.
Malaysia: Malaysia is a high-power distance country, which means that there is a strong belief in hierarchy and respect for authority. This can make it difficult for leaders to empower their employees and encourage them to take risks.
China: China is also a high-power distance country, and it is also a collectivist society, which means that people place a strong emphasis on group harmony and cooperation.
Saudi Arabia: Saudi Arabia is a high-power distance country, and it is also a high-uncertainty avoidance country, which means that people have a strong need for structure and predictability. This can make it difficult for leaders to be flexible and adapt to change.
Japan: Japan is a high-power distance country, and it is also a collectivist society. This can make it difficult for leaders to be assertive and take risks.
Transformational leadership is a leadership style that inspires and motivates employees to achieve extraordinary results. It is based on the belief that people have the potential to do great things, and that leaders can help them to reach their full potential.
In high-power distance cultures, people are accustomed to following orders and they may not be comfortable with leaders who encourage them to think for themselves. In collectivist cultures, people place a strong emphasis on group harmony and cooperation, and they may not be comfortable with leaders who stand out from the crowd or challenge the status quo.
If you are a leader who wants to implement transformational leadership, it is important to be aware of the cultural challenges that you may face. You can overcome these challenges by being patient, understanding, and respectful of the cultural norms.
To learn more about leadership click here; brainly.com/question/32800587
#SPJ11
Which of the following terms best describe a grower of potatoes
A. Manufacturer
B. Wholesaler
C. Distribution center
D. Retailer
Answer:
A
Explanation:
Definition of a manufacturer: a person or company that makes goods for sale.
A grower of potatoes is best described as Manufacturer. Thus the correct option is A.
What is the manufacturer?A manufacturer is referring as the first person in the distribution channel who performs the work related to the production and assembly of goods in industries or factories and is sent to different agents.
A Wholesaler is referred to as the second individual in the Distribution system who purchases the commodities in bulk and sends them to retailers or small bsuiness men. This bulk purchasing helps to save teh costs.
Retailers are business entities that have a direct contract with the customers and who purchase goods from wholesalers in small quantities and sell to the ultimate customer. They receive direct feedback on products
Therefore, option A is appropriate.
Learn more about Wholesaler, here:
https://brainly.com/question/15561836
#SPJ2
BTB Inc., expects earnings at the end of this year of $4.19 per share, and it plans to pay a $2.43 dividend at that time. It will retain $1.76 per share of its earnings to reinvest in new projects with an expected return of 15% per year. Suppose it will maintain the same dividend payout rate, retention rate, and return on new investments in the future and will not change its number of outstanding shares.
(a) What growth rate of earnings would you forecast for BTB?
(b) If BTB’s equity cost of capital is 12.2%, what price would you estimate for BTB stock today
(c) Suppose BTB instead paid a dividend of $3.43 per share at the end of this year and retained only $0.76 per share in earnings. If BTB maintains this higher payout rate in the future, what stock price would you estimate now? Should BTB raise its dividend?
(d) What was BTB’s payout ratio initially and what would be in part (c )?
To forecast the growth rate of earnings for BTB, we can use the dividend payout rate and the return on new investments.
If BTB's equity cost of capital is 12.2%, we can estimate the stock price today.
If BTB pays a higher dividend of $3.43 per share and retains only $0.76 per share in earnings, the stock price estimate will be $33.34. we can calculate the new stock price estimate and evaluate whether BTB should raise its dividend.
The initial payout ratio was 58% and the revised payout ratio in part (c) is 82%.
To forecast the growth rate of earnings for BTB, we can use the dividend payout rate and the return on new investments. The dividend payout rate is the ratio of the dividend per share to the earnings per share. In this case, the dividend payout rate is $2.43 / $4.19 ≈ 0.58.
The retention rate is 1 - dividend payout rate, which is 1 - 0.58 = 0.42. Since the return on new investments is 15% per year, we can multiply the retention rate by the return on new investments to get the growth rate: 0.42 * 0.15 = 0.063, or 6.3%. Therefore, the forecasted growth rate of earnings for BTB is 6.3%.
To estimate the stock price today, we can use the dividend discount model. The stock price is equal to the present value of future dividends, discounted by the equity cost of capital. Using the given equity cost of capital of 12.2% and the expected dividend of $2.43, we can calculate the stock price: $2.43 / (0.122 - 0.063) = $41.47.
If BTB instead paid a dividend of $3.43 per share and retained only $0.76 per share in earnings, we can recalculate the stock price estimate. The dividend payout rate is now $3.43 / $4.19 ≈ 0.82, and the retention rate is 1 - dividend payout rate, which is 1 - 0.82 = 0.18. The growth rate is 0.18 * 0.15 = 0.027, or 2.7%.
Using the dividend discount model with the revised numbers, the stock price estimate is $3.43 / (0.122 - 0.027) = $33.34. Whether BTB should raise its dividend depends on factors such as its financial goals, reinvestment opportunities, and shareholder preferences.
The initial payout ratio is the dividend per share divided by the earnings per share, which is $2.43 / $4.19 ≈ 0.58, or 58%. In part (c), the revised payout ratio is $3.43 / $4.19 ≈ 0.82, or 82%. Therefore, the initial payout ratio was 58% and the revised payout ratio in part (c) is 82%.
Learn more about equity here:
https://brainly.com/question/32234513
#SPJ11
write in brief about training
Answer:
Training is teaching, or developing in oneself or others, any skills and knowledge or fitness that relate to specific useful competencies. Training has specific goals of improving one's capability, capacity, productivity and performance.
Explanation:
Hope it helps you:))
What are the goals of government regulation?
low unemployment, price stability,
economic growth
O high unemployment, price instability,
economic growth
low unemployment, price stability,
economic steadiness
O high unemployment, price instability,
economic steadiness
Answer: A) low unemployment, price stability, economic growth
Explanation: Government regulation attempts to promote growth, full employment, and price stability for the well-being of the citizens
The goals of an ideal government while making regulations shall include the following purposes,
low unemployment, price stability,economic growth.Therefore, the option A holds true.
What is the significance of government goals?The goals of a government can be referred to or considered as the qualitative and quantitative targets set by the government in order to foresee better conditions in the future. These are backed by economic plans and regulations.
For a developing or a developed government, the goals must be economically based while being regulated. These goals must include reduced poverty and unemployment in order to achieve a healthy economic growth.
Therefore, the option A holds true and states regarding the significance of the goals of a government.
Learn more about government goals here:
https://brainly.com/question/526427
#SPJ2
When Walmart issued new standards for livestock products that were raised on food without antibiotics or artificial growth hormones, it considered multiple ________, including the ranchers that supply the food, its customers, and animal welfare groups. Group of answer choices
Walmart has issued new standards for livestock products that are raised on food without antibiotics or artificial growth hormones. The company has considered multiple factors while doing so, including the ranchers that supply the food, its customers, and animal welfare groups.
Walmart’s decision to introduce new standards for the food that the company supplies its customers with is in response to the growing concern of the public about the welfare of the animals used to produce food. The company has realized that its customers want meat that is produced in a more humane manner and want to know what goes into the products they buy.This initiative is also driven by Walmart’s commitment to sustainability. The company is a major player in the retail industry and has a responsibility to act in a sustainable manner.
By implementing new standards, Walmart is encouraging its suppliers to adopt sustainable practices that will help preserve the environment and protect the welfare of animals used for food.The new standards also consider the ranchers who supply the food. The standards aim to ensure that the food is produced in a way that is cost-effective for the suppliers. The company has worked with the ranchers to develop these standards so that they are achievable and practical. In doing so, Walmart is supporting the local economy and promoting sustainable farming practices.
To know more about standards visit:
https://brainly.com/question/31979065
#SPJ11
The goal of a pitch Deck is to get investor’s attention true or false
Answer:
true
Explanation:
True. A pitch deck is a visual presentation that is used to provide potential investors with an overview of a company's business plan, financials, and growth potential. The goal of a pitch deck is to capture the investor's attention and interest, and to persuade them to invest in the company. A good pitch deck should be clear, concise, and persuasive, and should highlight the key points that investors need to know in order to make an informed decision about whether to invest in the company.
To reduce the time repair technicians need to spend traveling from one customer to the next, an appliance repair company could make a ___________ , becoming more efficient and hopefully more profitable.
To reduce the time repair technicians need to spend traveling from one customer to the next, an appliance repair company could make a geographic realignment or reorganization.
By grouping technicians together based on their location and the location of the customers they serve, the company can reduce travel time and increase the number of customers each technician can serve in a day. This type of realignment could also lead to more efficient use of resources, better customer service, and increased profitability. Additionally, it could help the company to better manage its inventory, scheduling, and other business processes, ultimately leading to improved operations and a stronger competitive position in the market.
Learn more about technicians
https://brainly.com/question/14290207
#SPJ4
What marketing strategy decisions do marketers have with product lines?
Which of the following sets is most important to consider when choosing a career?
(A) needs and demographics
(B) hobbies and friends
(C) diversity and interests
(D) personal values and work values
The sets that is most important to consider when choosing a career is (C) diversity and interests.
What is a career ?Career can be described as the occupation that ios been undertaken for a significant period whgich one can focus on, through ouut hios or her life with opportunities for progress.
It should be noted that when choosing ba career one should be able to seek for the things that interest you about tyhe field because ythis will help you when the journey is getting tough because to get to the peak of the career can not be seen as one that ios easy.
Therefore, option C is correct.
Learn more about career at:
brainly.com/question/6947486
#SPJ1
ERP is now about enterprise applications 20 Multiple Choice 8 003735 ntegration development deployment interfaces.
ERP is now about enterprise applications: integration, means the option B is correct.
Businesses utilize the enterprise resource planning (ERP) software to coordinate and manage the key elements of their operations. Many ERP software programs are essential to businesses because they assist in the implementation of resource planning by integrating all the operations required to manage their businesses into a single system. Planning, inventory purchases, sales, marketing, finance, and other activities can all be integrated into an ERP software system. The many business operations can be integrated via ERP software. Since ERP solutions have developed through time, many of them are now often web-based programs that users may access from anywhere. Free communication between business units, a single source of information, and precise, real-time data reporting are some advantages of ERP. There are numerous.
Learn more about ERP here:
https://brainly.com/question/29417417
#SPJ4
The complete question is here:
ERP is now about enterprise applications:
A. networking
B. integration
C. interfaces
D. deployment
E. development
a marketing plan and operating budget are two components of
a.a long range planning
b. a business plan
c. short range planning
d. a staff planning