Consider the following work breakdown structure: Activity A B С D Start Node 1 1 2 3 Finish Node 2 3 Optimistic 41 54 58 32 Duration (days) Most Likely 50 60 70 41 Pessimistic 59 66 82 44 4 4 What is the probability that this project will be completed within 130 days? Multiple Choice O .9544 .8413 O 9987 .9772 190

Answers

Answer 1

The probability that this project will be completed within 130 days is 0.8413.

How to find probability of project duration

Expected duration (ED) = (Optimistic + 4 x Most Likely + Pessimistic) ÷ 6.

Activity A

Optimistic = 41

Most Likely = 50

Pessimistic = 59ED = (41 + 4 × 50 + 59) ÷ 6 = 50

Duration = 50

Activity B

Optimistic = 54

Most Likely = 60

Pessimistic = 66ED = (54 + 4 × 60 + 66) ÷ 6 = 60

Duration = 60

Activity C

Optimistic = 58

Most Likely = 70

Pessimistic = 82ED = (58 + 4 × 70 + 82) ÷ 6 = 70

Duration = 70

Activity D

Optimistic = 32

Most Likely = 41

Pessimistic = 44ED = (32 + 4 × 41 + 44) ÷ 6 = 41

Duration = 41

Total Project Duration = 50 + 60 + 70 + 41 = 221

Expected time for completing project = 221 days

The standard deviation of the critical path is obtained by using the following formula:

σ = P - O/6

Where σ represents the standard deviation of the critical path, P represents the pessimistic time, and O represents the optimistic time.

σ = 66 - 54/6 = 2.

Then, the probability that this project will be completed within 130 days:

z = (130 - 221) / 2 = -45.5P(z < -45.5) = 0 (due to negative value)

P(z < -4.5) = 0 (from normal distribution table)

Thus, the probability that this project will be completed within 130 days is 0.8413.

Learn more about project duration at

https://brainly.com/question/31063767

#SPJ11


Related Questions

Two functions are represented below: f(x) = 3x + 2 g(x) = 27-1 Which of the following is true? overequal intervals f(x) is exponential because it grows by equal differences oversequal intervals O g(x) is exponential because it grows by equal differences over equal intervals O f(x) is exponential because it grows by equal factors over equal intervals O g(x) is exponential because it grows by equal factors over equal intervals​

Two functions are represented below: f(x) = 3x + 2 g(x) = 27-1 Which of the following is true? overequal

Answers

Answer: g(x) is exponential because it grows by equal factors over equal intervals​

Step-by-step explanation:

Find the value of h(-67) for the function below.

h(x) = -49x − 125

A.
-3,408
B.
3,158
C.
3,283
D.
-1.18

Answers

Answer:

B.   3,158

Step-by-step explanation:

h(x) = -49x − 125

Let x = -67

h(-67) = -49(-67) − 125

          =3283-125

          = 3158

Answer:

Answer B

Step-by-step explanation:

To find the value of h(-67) for the function h(x) = -49x - 125,

we substitute -67 for x in the function and evaluate it.

h ( - 67 ) = - 49 ( - 67 ) - 125

Now we can simplify the expression:

h ( -67 ) = 3283 - 125

h ( -67 ) = 3158

Which of the following are in correct order from greatest to least? startfraction pi over 2 endfraction, 330°, startfraction 5 pi over 3 endfraction, startfraction 7 pi over 6 endfraction, startfraction 2 pi over 3 endfraction startfraction 5 pi over 3 endfraction, startfraction 7 pi over 6 endfraction, startfraction 2 pi over 3 endfraction, startfraction pi over 2 endfraction , 330° startfraction pi over 2 endfraction, startfraction 2 pi over 3 endfraction, startfraction 7 pi over 6 endfraction, startfraction 5 pi over 3 endfraction, 330° 330°, startfraction 5 pi over 3 endfraction, startfraction 7 pi over 6 endfraction, startfraction 2 pi over 3 endfraction, startfraction pi over 2 endfraction

Answers

The angles are in correct order greatest to least is 330°, 5π/3, 7π/6, 2π/3, π/2.

What is a reference angle?

A reference angle means the measure of the smallest, positive, acute angle that is formed by the terminal side of the angle. Therefore, positive reference angles possess terminal sides in the first quadrant.

Lets convert all the values into degrees

330° = 330°

π/2 = 180/2 = 90°

5π/3 = 300°

7π/6 = 210°

2π/3 = 120°

Arrange them from greatest to lowest.

330°, 300°, 210°, 120°, 90°

or

330°, 5π/3, 7π/6, 2π/3, π/2

Hence, the angles are in correct order greatest to least is 330°, 5π/3, 7π/6, 2π/3, π/2.

To know more about reference angles click the link given below.

https://brainly.com/question/16560063

Answer:

d

Step-by-step explanation:

thats what the guy above me said

PLEASE HELPPP!!!!! will give brainiest

PLEASE HELPPP!!!!! will give brainiest

Answers

Answer:

See below

Step-by-step explanation:

Draw segments XY and XZFind perpendicular bisector of segments XY and XZPerpendicular bisectors of XY and XZ intersects each other at a point say O. Taking O as center and OY = OX = OZ as radius draw a circle which will pass through the points X, Y and Z. This is the required circle.

Use conditional proof and the eighteen rules of inference to derive the conclusions of the following symbolized arguments. Having done so, attempt to derive the conclusions without using conditional proof.
1. N ⊃ O
2. N ⊃ P / N ⊃ (O • P)

Answers

The conclusion of the symbolised argument is that N implies (O and P). This can be proven using conditional proof and the eighteen rules of inference, or using the rule of conjunctive simplification.

The symbolic argument's conclusion is that N implies (O and P). This can be demonstrated using conditional proof and the eighteen inference rules.

Proof:

1. N ⊃ O (Premise)

2. N ⊃ P (Premise)

3. N (Assumption)

4. O (1,3 Modus Ponens)

5. P (2,3 Modus Ponens)

6. O•P (4,5 Conjunction)

7. N ⊃ (O•P) (3-6 Conditional Proof)

8. N ⊃ (O•P) (2,7 Disjunctive Syllogism)

This leads us to the conclusion that N implies (O and P).

Without the use of conditional proof, the identical result can be reached. The conjunctive simplification rule can be used to do this.

Proof:

1. N ⊃ O (Premise)

2. N ⊃ P (Premise)

3. N (Assumption)

4. O (1,3 Modus Ponens)

5. P (2,3 Modus Ponens)

6. O•P (4,5 Conjunction)

7. N ⊃ (O•P) (Conjunctive Simplification)

Therefore, we have derived the conclusion that N implies (O and P).

Complete Question:

Use conditional proof and the eighteen rules of inference to derive the conclusions of the following symbolized arguments. Having done so, attempt to derive the conclusions without using conditional proof.

1. N ⊃ O

2. N ⊃ P / N ⊃ (O • P)

To learn more about simplification visit:

https://brainly.com/question/30231919

#SPJ4

Can you help me thank you :)

Can you help me thank you :)

Answers

Answer:

16

Step-by-step explanation:

\(\sqrt{121}\) + \(\sqrt[3]{125}\)

= 11 + 5

= 16

The product of 1/7
and its additive inverse is

Answers

Answer:

the additive inverse of 1/7 is -1/7

1/7 x -1/7 = -1/49

Problem 6 (16 points). An individual opens a savings account with an initial investment of $500. The bank offers her an annual interest rate of 9%, which is continuously computed. She decides to deposit $200 every month. a) Write an initial value problem that models this investment over time. b) Solve the IVP.
c) What is the value of the investment in 2 years? d) After the 2 year mark, she increases her monthly investment to $300. What is the value of the investment a year later? Show all your work for full credit; you may use a calculator for this problem. Problem 7 (16 points). Solve the following IVP: ycosx−2xe y coz x − 2x eʸ -6x² - (x² eʸ - sin x - 4) yᶦ = 0; y (π) = 0

Answers

The investment problem is modeled by an initial value problem (IVP) where the rate of change of the investment is determined by the initial investment, monthly deposits, and the interest rate.

a) The investment problem can be modeled by an initial value problem where the rate of change of the investment, y(t), is given by the initial investment, monthly deposits, and the interest rate. The IVP can be written as:

dy/dt = 0.09y + 200, y(0) = 500.

b) To solve the IVP, we can use an integrating factor to rewrite the equation in the form dy/dt + P(t)y = Q(t), where P(t) = 0.09 and Q(t) = 200. Solving this linear first-order differential equation, we obtain the solution for y(t).

c) To find the value of the investment after 2 years, we substitute t = 2 into the obtained solution for y(t) and calculate the corresponding value.

d) After 2 years, the monthly deposit increases to $300. To find the value of the investment a year later, we substitute t = 3 into the solution and calculate the value accordingly.

Learn more about Initial Value Problem: brainly.com/question/31041139

#SPJ11

What is the domain and range of each relation?

What is the domain and range of each relation?

Answers

Answer:

Table:

Domain: {-1, 3, 6}

Range: {4, 5, 6}

Set of coordinates:

Domain: {-4, -3, 1}

Range: {1, 3, 4}

points a (3, 3) and b (3, 6) are two vertices of rectangle abcd. the rectangle is dilated by a scale factor of 1/3. what are the coordinates of a'?

Answers

The coordinates of a' after scaling factor of 1/3 is a'(1,1).

Given:

points a (3, 3) and b (3, 6) are two vertices of rectangle abcd. the rectangle is dilated by a scale factor of 1/3.

Rectangle:

A rectangle is a type of quadrilateral, whose opposite sides are equal and parallel.

Scale factor :

A scale factor is defined as the ratio between the scale of a given original object and a new object, which is its representation but of a different size.

scale factor = 1/3

= (3*1/3 , 3*1/3)

= (3/3 , 3/3)

= (1,3/3)

= (1,3)

Therefore the coordinates of a'(1,1).

Learn more about the coordinates here:

https://brainly.com/question/27749090

#SPJ4

scaling, when it applies to graphics, means changing the vertical or horizontal size of the graphic by a percentage. true or false

Answers

False. Scaling, in the context of graphics, refers to the process of resizing an image or graphic while maintaining its aspect ratio. It involves changing both the vertical and horizontal size of the graphic by the same percentage.

When scaling a graphic, the goal is to resize it proportionally, preserving the original aspect ratio. This means that both the vertical and horizontal dimensions are changed by the same factor or percentage. For example, if an image is scaled by 50%, both its height and width will be reduced by 50% of their original values. This ensures that the graphic maintains its original proportions and does not appear distorted.

Scaling graphics is commonly used in various applications, such as graphic design, image editing, and web development, to resize images without distorting their appearance. It allows for consistent resizing across different devices or platforms while maintaining the integrity of the original graphic.

Learn more about proportions here:

https://brainly.com/question/31548894

#SPJ11

Mr. Gallagher purchased snacks at the theater. If
he handed the cashier a 20-dollar bill and received
$1.83 in change, what was his total?

Answers

Answer: $18.17

Step 1: Subtract 1 dollar.

$20 - $1 = $19

Step 2: Subtract 83 cents.

$19.00 - $0.83 = $18.17

Answer = $18.17

A photo of a beetle in science is increased to 66% as large as the actual size. If the beetle is 15 millimeters, what is the size of the beetle in the photo?

A photo of a beetle in science is increased to 66% as large as the actual size. If the beetle is 15 millimeters,

Answers

The size of the beetle in the photo can be calculated by multiplying the actual size of the beetle (15 mm) by the percentage increase (66%). The calculation is as follows: 15 mm x 66% = 9.9 mm. Therefore, the size of the beetle in the photo is 9.9 mm.

To understand this calculation better, it is helpful to break it down into its individual components. The actual size of the beetle is 15 mm, which is the size of the beetle before it is increased. The percentage increase is 66%, which means that the size of the beetle will be increased by 66% of its original size. The calculation then multiplies the actual size of the beetle (15 mm) by the percentage increase (66%) to determine the size of the beetle in the photo (9.9 mm).This calculation can be used to determine the size of any object in a photo that has been increased to a certain percentage of its original size. All that is needed is the actual size of the object and the percentage increase. The calculation can then be used to determine the size of the object in the photo.

Learn more about percentage here:

https://brainly.com/question/26352729

#SPJ1

g (x) = x 3 - 3
what is the value of x when g (x) = 24? enter in the box

Answers

Answer:

69.

im not kidding, haha, good luck!

If a laptop computer regularly cost $1096 and it’s on sale for $736 what percentage discount is being given round your answer to the nearest hundredth when necessary

If a laptop computer regularly cost $1096 and its on sale for $736 what percentage discount is being

Answers

If a laptop computer regularly cost $1096 and it’s on sale for $736 what percentage discount is being given round your answer to the nearest hundredth when necessary

step 1

Find out the difference

1096-736=$360

step 2

In this problem

$1,096 represent the 100%

so

applying proportion, find out how much percentage represent the difference

100%/1,096=x/360

solve for x

x=100*360/1,096

x=32.85%

A store is selling 5 dozen bagels for $48. Based on this price, what is the cost for one bagel

Answers

Answer:

80 cents

Step-by-step explanation:

There are 12 in a dozen

5*12=60

48/60=.8

So, the answer is 80cents

Answer:

$.80 or 80 cents

Step-by-step explanation:

This is very simple, a dozen is 12 bagels, 12 multiplied by 5 is 60. Next, you'd simply divide, 48 divided by 60. You're answer would be $.80. Hope this helped :)


(sin(\theta )+cos(\theta )-tan(\theta ))/(sec(\theta )+csc(\theta )-cot(\theta )) given that tan\theta =-(4)/(3) in quadrant II

Answers

We have to find the value of  `(sinθ+cosθ−tanθ)/(secθ+cscθ−cotθ)`

Let's find all trigonometric ratios:

We can say that:

\($$\tan \theta= \frac{opp}{adj}= \frac{-4}{3}$$$$\text\)

{Using the Pythagorean Theorem we can find the hypotenuse }

\($$$$\text{Hypotenuse = } \sqrt{(-4)^2+(3)^2}\)

\(= \sqrt{16+9}\)

= \(\sqrt{25}\)

=\(5$$$$\)

Substituting the values of sinθ, cosθ and tanθ in `

\(= \frac{\frac{3}{5} + \frac{-4}{5} - \frac{-4}{3}}{\frac{-4}{5} + \frac{5}{3} - \frac{-3}{4}}$$$$\)

\(=\frac{\frac{9}{15} + \frac{-12}{15} + \frac{20}{15}}{\frac{-16}{20} + \frac{25}{12} + \frac{3}{4}}$$$$\)

\(=\frac{\frac{17}{15}}{\frac{-14}{15}}$$$$\)

\(=-\frac{17}{14}$$\)

Therefore, \(`(sinθ+cosθ−tanθ)/(secθ+cscθ−cotθ)\)` is equal to

`-17/14` when `tanθ=−43` (Quadrant II).

To know more about Pythagorean visit:

https://brainly.com/question/28032950

#SPJ11

plssss help with all thiss​

plssss help with all thiss

Answers

Step-by-step explanation:

8, 12(3-x)=48

36-12x=48

-12x=48-36

-12x=12 both side divideos by -12

-12x/-12=12/-12

x= 1

9, x/7=4.5 cris cross

x=31.5

10,5(x-3)=45

5x-15=45

5x=45+15

5x=60 both side divided by 5

5x/5=60/5

x=12

11,-3(x-3)=45

-3x+3=45

-3x=45-3

-3x=42 both side divided by -3

-3x/-3=42/-3

x=14

12,14y-8=13

14y=13+8

14y=21 both side divided by 14

14y/14=21/14

y=1.5

13,3m=5m-8/5

3m-5m=-8/5

-2m=-8/5 cris cross

-10m=-8 both side divided by -10

-10m/-10=-8/-10

x=0.8

8) X= -1

Divide both sides by 12, move the constant to the right, and subtract

9) X= 31.5

Multiply both sides by 7, reduce and multiply

10) X= 12
11) X= -12
12) y= 3/2
13) y= 2/3 I believe if the cropped out number is 6


Hope this helps:)

NOTE: For All Calculations In This Lab, Use The Approximation Of 62,500 Inches To The Mile When Necessary. ALWAY

Answers

By using the approximation of 62,500 inches to the mile, you can simplify and expedite various calculations involving distances and conversions between inches and miles, providing a convenient tool for numerical analysis and problem-solving

The approximation of 62,500 inches to the mile is commonly used in various calculations, especially in scenarios where conversions between inches and miles are involved. This approximation simplifies the conversion process and allows for easier calculations.

For example, if you need to convert a distance from miles to inches, you can simply multiply the number of miles by 62,500 to obtain the equivalent distance in inches. Conversely, if you have a measurement in inches and want to convert it to miles, you divide the number of inches by 62,500 to get the distance in miles.

Additionally, this approximation can be useful in other applications, such as determining the number of inches in a given number of miles, or calculating the length of a specific distance in miles based on its measurement in inches.

Learn more about measurement here:

https://brainly.com/question/28913275

#SPJ11

.

Your younger sibling runs up to you and excitedly exclaims, "I'm thinking of a number. If I add it to the number 2 ten times, that is, 2 + my number + my number + my number, and so on, then the answer is 2. What is my number?" You almost immediately answer, "zero," but are you sure? Can you find a different number (other than zero) that has the same property? If not, can you justify that your answer is the only correct answer?

Answers

Answer:

\(x = 0\)

Step-by-step explanation:

Given

Represent the number with x.

So:

\(2 + x + x + x + x + x + x + x + x + x + x = 2\)

or

\(2 + 10x = 2\)

We want to solve for x

Subtract both sides by 2

\(2 - 2 + 10x = 2 - 2\)

\(10x = 0\)

Solve for x

\(x = \frac{0}{10}\)

\(x = 0\)

No other number aside 0, satisfy the property.

Quadrilaterals DONT and WALK are similar. Find the length of side DO.

(15 Points)

Send ASAP PLSS

Quadrilaterals DONT and WALK are similar. Find the length of side DO.(15 Points)Send ASAP PLSS

Answers

Answer is B 9
X/3=15/5
45/5
x=9
So answer B
B is the answerrrrrrrrrrr

Mr. and Mrs. Doran have a genetic history such that the probability that a child being born to them with a certain trait is 0.82. If they have four children, what is the probability that exactly two of their four children will have that trait? Round your answer to the nearest thousandth.

Answers

Using binomial distribution, the probability of exactly two of their four children having the trait is 0.13 (rounded to the nearest thousandth).

What is the probability that a child born to them with a certain trait is 0.82

This is a binomial distribution problem with n = 4 trials (number of children) and p = 0.82 probability of success (having the trait) for each trial.

The probability of exactly two children having the trait can be calculated using the binomial distribution formula:

P(X = 2) = (4C2) * 0.82^2 * (1 - 0.82)^(4-2)

where (4C 2) is the number of ways to choose 2 children out of 4.

Using a calculator or statistical software, we get:

P(X = 2) = (4 C 2) * 0.82^2 * (1 - 0.82)^(4-2)

= 6 * 0.82^2 * 0.18^2

= 0.13

Learn more on binomial distribution here;

https://brainly.com/question/15246027

#SPJ1

PLS PLS HELP OMG PLSS

PLS PLS HELP OMG PLSS

Answers

The time that Natasha will be able to finish the last piece of equipment will be 8.15 pm

How to calculate the time?

It should be noted that the following information can be deduced based on the information given:

Steeper = 18 minutes

Treadmill = 25 minutes

Rower = 27 minutes

Bike = 1 hour 5 minutes = 65 minutes

Total minutes = 18 + 25 + 27 + 65 = 135 minutes = 2 hours 15 minutes

It should be noted that there's an interval of 5 minutes between each equipment. The time for all the equipment will be:

= 5 × 3 = 15 minutes

Therefore since the starting time is 5.45 pm, the ending period will be:

= 5.45 + 15 minutes + 2 hours 15 minutes

= 8.15 pm

Learn more about time on:

brainly.com/question/26314009

#SPJ1


_(blank)_ = Cost of Attendance (COA) − Expected Family
Contribution (EFC)

Answers

The term that should be placed in the blank in the given question is the "Financial need."

Financial Need is the difference between the Cost of Attendance (COA) and the Expected Family Contribution (EFC). In simpler terms, it is the total amount of money that is required to fund the student's college education, minus the family's contribution, as determined by the FAFSA (Free Application for Federal Student Aid).COA (Cost of Attendance): COA is a detailed evaluation of all the costs involved in pursuing higher education, including tuition fees, housing and meal costs, textbooks, lab equipment, and transportation costs. However, students must note that the COA may vary from one college to another and depend on the program of study.EFC (Expected Family Contribution): The Expected Family Contribution (EFC) is the total amount of money that the student and their family are expected to contribute to their higher education costs, as per the Free Application for Federal Student Aid (FAFSA). The EFC takes into account factors such as family income, assets, benefits, and other financial data to determine the student's eligibility for financial aid.

To know more about Financial need, visit:

https://brainly.com/question/31545420

#SPJ11

HELP ME ASAP I NEED HELP

HELP ME ASAP I NEED HELP

Answers

Answer:

distance = 7.07 units

Step-by-step explanation:

x difference = 7

y difference = -1

using the Pythagorean theorem:

7² + -1² = d²

d² = 49 + 1 = 50

d = 7.07

Answer:

7.1

Step-by-step explanation:

distance between the x is 7 and y is 1

And to find the hypotenuse, you use the quadratic formula, 7^2 + 1^2 = c^2

c=50

and take the square root, which is 7.071, rounds to 7.1

find dz dt by the chain rule where z = cosh2 (xy), x = 1 2 t, and y = e t .

Answers

To find dz/dt using the chain rule, we need to calculate the derivatives of z with respect to x and y separately, and then multiply them by the derivatives of x and y with respect to t.

Given:

z =  \(cosh^{2} (xy)\)

x = (1/2)t

y = \(e^{t}\)

Let's start by finding the partial derivatives of z with respect to x and y:

∂z/∂x = \(2cosh(xy) * sinh(xy) * y\)  (using the chain rule)

∂z/∂y = \(2cosh(xy) *sinh(xy)*x\)    (using the chain rule)

Next, let's find the derivatives of x and y with respect to t:

dx/dt = 1/2

dy/dt = \(e^{t}\)

Finally, we can use the chain rule to find dz/dt:

dz/dt = (∂z/∂x)(dx/dt) + (∂z/∂y)(dy/dt)

      = \(2cosh(xy) *sinh(xy)*y*(1/2) + 2cosh(xy)*sinh(xy)*x*e^{t}\)

     

Now, substitute the given expressions for x and y:

\(dz/dt = 2cosh((1/2)t*e^{t} * sinh((1/2)t*e^{t} *(1/2)* + 2cosh((1/2)t*e^{t} *sinh((1/2)t*e^{t} *((1/2)t)\)

Simplifying further, we have:

\(dz/dt = cosh((1/2)t*e^{t} *sinh((1/2)t*e^{t})* e^{t} + cosh((1/2)t* e^{t}*sinh((1/2)t*e^{t}* ((1/2)t)\)

This is the expression for dz/dt using the chain rule with the given values of x and y.

To know more about chain rule refer here:

https://brainly.com/question/31585086?#

#SPJ11

Find the next two terms in this
sequence.
5,-5,10,-10,15,[ ? 1,[]
what’s the next two terms?

Find the next two terms in thissequence.5,-5,10,-10,15,[ ? 1,[]whats the next two terms?

Answers

5,-5,10,-10,15,-15,20

Hopefully that helps

in the expression 4x + (2x - 9) - 1/2x there are ___ term(s), ____ constant(s) and ____ coefficient(s).​

Answers

Answer:

4 terms, 1 constant, 3 coefficients.

Step-by-step explanation:

A truck uses 1 gallon of diesel for every 12 miles traveled. The amount of diesel left in the gas tank, r gallons, after traveling s miles is give by s= 120-12r.

Answers

The question has missing details. However, general questions that could be asked is as follows:

(1) The number of miles traveled after using (say) 5 gallons

(2) The number of gallons used after traveling for (say) 36 miles

Answer:

See Explanation

Step-by-step explanation:

Given

\(s = 120 - 12r\)

A linear equation is represented as:

\(y = c + mx\)

Where

\(c =y\ intercept\) and

\(m = slope.\)

c, in this question represents the initial capacity of the tank.

So, the initial capacity is 120 liters

Solving (a): r = 5

\(s = 120 - 12r\)

\(s = 120 - 12 * 5\)

\(s = 120 - 60\)

\(s = 60\)

60 miles traveled

Solving (b): s = 36

\(s = 120 - 12r\)

\(36 = 120 - 2r\)

Collect like terms

\(2r =120 -36\)

\(2r =84\)

Solve for r

\(r = 42\)

42 gallons used

Please Help Me
SIMPLIFY

Please Help MeSIMPLIFY

Answers

Answer:

x+7/x+6

Step-by-step explanation:

Other Questions
Find at the terminals of the circuit According to the passage, what were George C. Marshall's military contributions during World War II? Check thethree correct options.He served as chief of staff of the US ArmyO He helped train US soldiers and airmen in modern warfareHe used and helped advance modern weaponry.O He led British and French Allied forces as well as US forces.He reduced the size of the US military from millions of troops to thousands what is the image of (-2, -5) after a reflection over the line y = x 25 precent of this square is shaded. What present of the square is not shaded albrecht inc. is a no-growth firm whose sales fluctuate seasonally, causing total assets to vary from $320,000 to $410,000, but fixed assets remain constant at $260,000. if the firm follows a maturity matching (or moderate) working capital financing policy, what is the most likely total of long-term debt plus equity capital? a. $320,000 b. $304,000 c. $288,800 d. $274,360 4. Choose the best answer.The atmosphere is a(n) _______ system.O triangularO closedO openO man-made Jamisyn is sitting down with their supervisor to complete their annual performance evaluation. The supervisor rates Jamisyn very poorly on attendance/tardiness. Jamisyn was 10 minutes late to work twice last week due to car trouble. Those two incidents are the only record during the last 12 months. According to this situation, which problem with performance appraisal is Jamisyn and the supervisor facing? Contrast Halo/horns Recency Using samples of 197 credit card statements, an auditor found the following: Use Table-A. Sample 1 2 3 4 Number with errors 5 3 6 9 a. Determine the fraction defective in each sample. (Round your answers to 4 decimal places.) Sample Fraction defective 1 2 3 4 b. If the true fraction defective for this process is unknown, what is your estimate of it? (Round your answer to 1 decimal place. Omit the "%" sign in your response.) Estimate % c. What is your estimate of the mean and standard deviation of the sampling distribution of fractions defective for samples of this size? (Round your intermediate calculations and final answers to 4 decimal places.) Mean Standard deviation d. What control limits would give an alpha risk of .03 for this process? (Round your intermediate calculations to 4 decimal places. Round your "z" value to 2 decimal places and other answers to 4 decimal places.) z = , to e. What alpha risk would control limits of .047 and .011 provide? (Round your intermediate calculations to 4 decimal places. Round your "z" value to 2 decimal places and "alpha risk" value to 4 decimal places.) z = , alpha risk = f. Using control limits of .047 and .011, is the process in control? yes no g. Suppose that the long-term fraction defective of the process is known to be 2 percent. What are the values of the mean and standard deviation of the sampling distribution? (Round your intermediate calculations and final answers to 2 decimal places.) Mean Standard deviation h. Construct a control chart for the process, assuming a fraction defective of 2 percent, using two-sigma control limits. Is the process in control? Yes No Hindi art integrated projectwrite 4 means of Agriculture, in Sikkim and stick pictures using two A4 sheets.PLEASE HELP IT'S URGENT the tremendous expansion of the middle classes in the 20 years after the end of world war ii was a result of A proportional relationship between the number of pounds of potatoes (x) and the price in dollars (y) is graphed, and the ordered pair (5, 4) is on the graphed line.Part A: What is the price of 1 pound of potatoes? Show your work. (8 points)Part B: What does the ordered pair (10, 8) on the graph represent? Explain in words. (2 points) Politics is known as the ""art of compromise"". List and explain three (3) compromises that the framers created at the constitutional convention in philadelphia in 1787?. Who was Maharashtra first cm Which context clue provides the best hint for the meaning of the underlined idiom in this excerpt?But Lauras inventing days were overthe rolling suitcase everyone else in the family remembersYoyo thinks of the speech her mother wrote as her last inventionafter that, her mother had passed on to Yoyo her pencil and pad HELP PLEASE! 25 points question!A teacher assigns the following experiment to a class. Draw an outline of a birds feather, and color one half of the outline with a thick coat from a wax crayon. Leave the other half uncolored. Next, sprinkle a few drops of water on both halves of the feather. You will observe that the water soaks into the plain paper. The waxy coat, however, allows the paper to remain dry. Water forms tiny beads on top of the wax instead of soaking through it.The results of the experiment are MOST USEFUL for explaining which of these functions of lipids in organisms? a. allowing water to pass through the cell membrane b. forming a waterproof covering on feathers, leaves, and fruits. c. providing energy for the cell d. replacing water in dry environments The molecular clock has limited usefulness for estimating divergence times among species in part due to the saturation of dna sequences. This occurs because. What are the four functions of the central bank?. plz help I don't have a lot of time left Dana wants to make her own spinner. what question can she ask to help guide her design?? PLEASE HELPP ASAP!! PLEASEE HELPPPP!! If tall eyeballs (T) are dominant to short eyeballs (t), give the genotype(s) for Mr. Krabs family members who have short eyeballs.A) TtB) ttC) TT or Tt D) TTI can only pick one of these